Errata
The errata list is a list of errors and their corrections that were found after the product was released.
The following errata were submitted by our customers and have not yet been approved or disproved by the author or editor. They solely represent the opinion of the customer.
Color Key: Serious technical mistake Minor technical mistake Language or formatting error Typo Question Note Update
Version | Location | Description | Submitted by | Date submitted |
---|---|---|---|---|
CH15 chapter 15: question 38 on stakeholder management |
the correct answer is Monitor Stakeholder Engagement. |
Bram De Backer | Feb 24, 2020 | |
CH15 chapter 15: question 20 on quality management |
the Process Improvement Plan is something which is not described in the PMBOK nor in the book. it can not be the right answer. this is problem from PMBOK v5 or older. |
Bram De Backer | Feb 24, 2020 | |
CH15 chapter 15: answer to question 21 on quality management |
the answer explains that [...] are all techniques of Acquire Project Team. |
Bram De Backer | Feb 24, 2020 | |
CH15 chapter 15: question 27 on stakeholder management |
The question ask about a Communication Management process. |
Bram De Backer | Feb 24, 2020 | |
all throughout the book |
there are various references to a "Quality Assurance" process. What is meant is the "Manage Quality" process. |
Bram De Backer | Feb 24, 2020 | |
CH16 question 17 of practice exam |
it is stated that "those costs have increased AC", meaning the police was already paid for (it's already in the actual costs). Currently the answer states "B. pay the police", which would mean you would pay twice for the same service? |
Bram De Backer | Feb 24, 2020 | |
all throughout the book |
Throughout the book (including in the Practice Exam!) you can find mention of the "Staffing Management Plan", except for what it really is (with the exception maybe of the screenshot under "The Resource Management Plan" in chapter 9). The reason is that no such plan exists in PMBOK v6. This should be the Resource Management Plan. |
Bram De Backer | Feb 24, 2020 | |
ch16 question 115 of practice exam and the answer |
the "records management system" does not exist in PMBOK v6. not in the least because it (according to the answer guide) belongs to the "Close Procurements" process, a process that also does not exist in PMBOK v6! |
Bram De Backer | Feb 24, 2020 | |
CH16 question 125 |
Even without looking in the book, you can *never* have a monitoring&control process without the original plan. |
Bram De Backer | Feb 24, 2020 | |
CH16 question 182 |
a "final product, result, or service" is also not something you can generate during "Close Project or Phase". What *is* something you generate is "a final product, result, or service *TRANSITION*". |
Bram De Backer | Feb 24, 2020 | |
Printed | Page 152 1st paragraph, 5th sentence. |
With PMBOK V6 PMI emphasizes that Lessons are created in the Manage Project Knowledge process in Integration, and the output is called the Lessons Learned Register. . In the Close Project or Phase process, as you're describing on P. 152, the Lessons Learned are not created, but rather the Lessons Learned Register that has been built throughout the project is finalized and added into the organization's Lessons Learned Register, where the Lessons Learned Registers from the other projects in your company are all stored. You do state that the lessons learned are made part of the company's OPAs in this process, but more specifically, it's the the Lessons Learned Repository. |
Jeff Furman, PMP Instructor | Sep 25, 2018 |
Printed | Page 609 Last Bullet Point |
The final bullet point in Bullet Points: Aiming for the Exam states that there are no executing processes in Risk Management. However, v6 of PMBOK added Implement Risk Responses (In the executing group), which is covered in this version of PMP starting on page 614. |
Drue | Feb 07, 2019 |
Printed | Page 750 Question 31 |
Option C states: Procurement closure means verifying that the project is complete or terminated; Close Project or Phase is the process of tying up all activities for every management process group. |
Alex G. | Oct 14, 2017 |
Printed | Page 765 Question 106 of practice exam |
Hi, |
Gajanan Desai | Nov 26, 2017 |