MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft® Office Project 2007

Errata for MCTS Self-Paced Training Kit (Exam 70-632): Managing Projects with Microsoft® Office Project 2007

The errata list is a list of errors and their corrections that were found after the product was released.

The following errata were submitted by our customers and have not yet been approved or disproved by the author or editor. They solely represent the opinion of the customer.

Color Key: Serious technical mistake Minor technical mistake Language or formatting error Typo Question Note Update

Version Location Description Submitted by Date submitted
Printed Page 35
Lesson Summary, Point No. 7:

"You can print Gantt Charts and Network Diagrams, and
each offers print options, including what dates to print."

But in actual scenario, the option of "Timescale (what dates to
print)" is available with Gantt chart only and not with the Network
Diagram.

Anonymous  Jul 08, 2010 
Printed Page 62
Exercise 3


Exercise 3, Step 1.
There is one too many opening parenthesis
((Optimistic + Pessimistic + (4*Expected))/6

should be:

(Optimistic + Pessimistic + (4*Expected))/6


Same goes for step 3 and 4

Jean-Francois Rivet  Jul 25, 2011 
Printed Page 62
Exercise 3


Exercise 3 step 8

"Expected" should be "Estimated"
On page 62, Step 8. of Exercise 3 uses an incorrect term.

Change:
"Note that the Expected Duration is 13 days."

To:
"Note that the Estimated Duration is 13 days."

Jean-Francois Rivet  Jul 25, 2011 
Printed Page 149
Last Paragraph

The "Work: eight hours" for the changed scenario should be "Work: 16 hours". Changing the number of painters should reduce the duration, not the work.

Anonymous  Aug 12, 2010 
Printed Page 155
Creating Cost and Resource Budgets section

This section (and associated Exercise 5) should be rewritten to follow more closely with this Microsoft video (which is much more clear on describing the subject): http://office.microsoft.com/en-us/project-help/watch-this-create-a-budget-HA010275127.aspx

Anonymous  Aug 12, 2010 
Printed Page 166
Exercise 2 paragraph

The word "project" in the second sentence should be "task".

Anonymous  Aug 12, 2010 
Printed Page 167
Paragraph after item number 5

The word "task" in the first sentence should be "project" to be consistent with the introduction paragraph to Exercise 4.

Anonymous  Aug 12, 2010 
Printed Page 376
Step 6.


Step 6. specifies wrong information order.

It says:
In the ID column, type the name of the master project followed by the task ID number of the external predecessor followed by a backslash


It should be:
In the ID column, type the name of the master project followed by a backslash followed by the task ID number of the external predecessor

Jean-Francois Rivet  Aug 14, 2011 
Printed Page 485
Case Scenario 4: Answer 3.


In explanation #4 for Case Scenario 4.

The last statement end with:
"forces Project to increase the task duration to four days"

it should be:
"forces Project to increase the task duration to eight days"

The scenario stated that a resources working two days (16 hours)
is reduced to 25% units (2 hours).
So, it takes 8 days to reach 16 hours

Jean-Francois Rivet  Aug 12, 2011