Errata

Head First PMP

Errata for Head First PMP

Submit your own errata for this product.

The errata list is a list of errors and their corrections that were found after the product was released.

The following errata were submitted by our customers and have not yet been approved or disproved by the author or editor. They solely represent the opinion of the customer.

Color Key: Serious technical mistake Minor technical mistake Language or formatting error Typo Question Note Update

Version Location Description Submitted by Date submitted
Printed Page 19
2nd Paragraph

Should the heading
"Gather product requirements"
read
"Gather project requirements"
or possibly "Continuously gather project requirements"
I usually think of "products" as tangible items resulting from a project e.g. building a house. Projects can also create new services or enhance existing ones. But it can be argued that a "product" is a service or other intangible outcome of a project. A "product" is (usually) one of the results of a project.

Steve Kato  Dec 06, 2016 
Printed Page 51
Exercise Box question number 2

Question 2 uses poor grammar.

It reads in part:

2.The company ...how to deploy the product of THEY project...

It should have used THEIR and not THEY

Patrick McShea  May 06, 2014 
Printed Page 67
Question #8

Chapter 2, Section Quiz Question #8 reads: A project COORDINATOR is having trouble securing programmers for HER PROJECT... which type of organization is she working in?

The answer according to the book is "Functional" - because she can't overrule the functional manager in overruling her request.

The answer should be "Weak" (also one of the choices), because she is a coordinator, and it is her project she is trying to allocate resources for, which implies that she has some authority, though still not enough to overrule the functional manager. If the answer was to be "functional", she would be an expediter, and would likely not have the responsibility of trying to get resources for anything.

Alex  Aug 03, 2017 
Printed Page 117
9th bullet point in bulleted list

Found this in the third edition, print format. (Form doesn't give a space to specify edition).

The ninth bullet in the bulleted list describes the "project management information system" as the enterprise environmental factor that "determines how work is assigned and makes sure that tasks are done in the right order."

However, this directly contradicts the correct information on p. 115, which says that "One of the enterprise environmental factors you'll use in the Integration Management processes is the work authorization system, which determines how your company assigns work to people and ensure that tasks are done properly and in the right order."

Judi Doyle  Oct 11, 2014 
Printed Page 123
3rd bulleted point

3rd edition, print.

Text indicates that the project management information system "defines how work is assigned to people."

That actually defines the work authorization system, which is a sub-system of the PMIS. Here are the definitions of each from the glossary of the PMBOK, 5th Ed.:

"Project Management Information System. An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes. It is used to support all aspects of the project from initiating through closing, and can include both manual and automated systems" (p. 554).

"Work Authorization System. A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents, tracking system, and defined approval levels needed to issue work authorizations" (p. 566).

To say that the PMIS defines how work is assigned is like saying that you hear with your body. You actually hear with your ear, and your ear is part of your body.

Judi Doyle  Oct 11, 2014 
Printed Page 140
Explanation of graphic in middle of page

3rd edition, print.

The explanation accompanying the graphic of "Accepted Deiverables" in the middle of the page says "The deliverables get accepted in the Verify Scope process."

In the Fifth edition of the PMBOK, the name of the "Verify Scope" (5.5) was changed to "Validate Scope" (see p. 470 in PMBOK 5th ed.).

Judi Doyle  Oct 11, 2014 
Printed Page 143
United States

Magnet choices on page 143 has choice of "project charter" but answers on 144 has choice of "contracts".

It should be contracts on both pages.

3rd Edition

Anonymous  Apr 04, 2014 
Printed, PDF Page 161
Explantion for question 17.

Explanation provided, "The project management information system is defined by the company, and it's external to the project."

I believe the correct sentence should be, "The work authorization system is defined by the company, and it's external to the project."

Sin Hua Wong  Mar 01, 2015 
Printed, PDF Page 161
First 2 side notes on the page

Arrows for side notes, "Remember that lessons learned are documented throughout the project, not just at the end! That's why they're part of Work Performance Information"

and

"When you close a process or phase, you need to make sure each deliverable has been accepted by the stakeholders."

should be pointing to explanation for question 18 instead of question 17.

Sin Hua Wong  Mar 01, 2015 
Printed Page 210
6th bullet in bulleted list

3rd edition, print

This bullet point says that "As you decompose the work, you find new information that needs to be added to the requirements document and the project scope statement. That information is treated as a change and goes through change control."

BUT on p. 209, the text indicates that "you don't have to go through change control until the baseline is approved." If you are still just decomposing work to create the WBS, it probably hasn't been approved yet, right? You WOULD have to update the requirements documentation and the project scope statement, obviously, but would you really need to invoke integrated change management at that point?

Judi Doyle  Oct 12, 2014 
Printed Page 211
3rd answer in the QA set

3rd edition, print.

Which is correct?

"...you don't have to go through change control until the baseline is approved. ... Until it's approved, you can make any changes you want" (p. 209).

OR

"Any time you run into a change to your scope, regardless of where you are in the process, you put it through change control" (p. 211).

Judi Doyle  Oct 12, 2014 
Printed Page 222
Answer magnet #8

3rd edition, print

Text says "How the team can change the way they do the work"

Should be "Now the team can change the way they do the work"

Judi Doyle  Oct 12, 2014 
Printed Page 223
Label on graphic for outputs of Validate Scope process

3rd edition, print

One of the outputs of the Validate Scope process is labeled "Verified deliverables". PMBOK 5th edition calls these "accepted deliverables". "Verified deliverables" are an input of Validate Scope and an output of Control Quality.

Judi Doyle  Oct 12, 2014 
Printed Page 227
conversation bubble for "Mike"

3rd edition, print

Mike says, "We verified the scope ..." but he should say "We validated the scope ..."

Judi Doyle  Oct 12, 2014 
Printed Page 236
answer # 3

Answer # 3 provided on the page is not in accordance what presented with 'anatomy of a change procedure' (page 230) . Namely, as per described procedure, step 3 (answer 3 ) should be 'compare the change against the baseline' not 'Get approval to make the change'.
As per decribed procedure, one needs to make imapct analysis before asking for change approval.

Anonymous  Jun 08, 2019 
PDF Page 241
Answer for question 26

In the sentence " The three outputs of Collect Requirements are requirements documentation and the requirements traceability matrix. ?Requirements Observations? isn?t really an output." it is said that there are 3 outputs for the "collect requirement" process.
When checking in the PMbook 5th edition page 117, there are only 2 output for this process mentioned: requirements documentation and the requirements traceability matrix.

Requirement management plan AND Requirement Observation that are shown as option A and D in the question are NOT outputs from the collect requirement process.
I think that both question and answer need to be reviewed.

Anonymous  Mar 11, 2014 
Printed Page 265
Top of page

The heading states that "Leads and lags add time between activities," but leads do not add time; they reduce it. As defined in the PMBOK Guide v. 5, a lead is “the amount of time whereby a successor activity can be advanced with respect to a predecessor activity."

Mike Stewart  Mar 30, 2016 
Printed Page 295
Network illustration at the top of the page

The duration for the "Design Invitations" activity is incorrect. It should be 4.

Veronica  Dec 07, 2016 
Printed Page 296
commentary on network diagram graphic at the bottom of the page; two comments

3rd edition, print

Text says, "First do the forward pass for both paths. When you do that, you get a different LF for Activity B, ..." You don't calculate LFs on forward passes. And, whether you are going forward or backward, looking at ES/EF or LS/LF, you won't get different values on Activity B; it isn't either a branching or a converging activity.

Next commentary text says, "We use Activity D to calculate the LF for Activity C because it has the lower LS." If you are looking to calculate a LF, you should be doing so in a backwards pass. If you are in a backwards pass, then you would be using Activity C to calculate the LF of Activity D, since Activity D is a predecessor of Activity C.

Judi Doyle  Oct 18, 2014 
Printed Page 325
Question 3

The answer for question 2 is ES of 13, for the same diagram how can question 3 have a LF of 10? which would be earlier than the earliest start.

Anonymous  Nov 02, 2015 
Printed Page 325
network diagram (quesions 2 and 3)

The values for "early start" and "early finish" of each activity (except G) are higher than the value for "late start" and "late finish". It should be contrary.

According to ES and EF the duration for the activities D and E is 3, but LS=3 and LF=4 the duration is only 2.

Anonymous  May 10, 2017 
Printed Page 365
first bolded sentence at bottom of page

3rd edition, print

The text says, "The actual cost of this project on May 14th is $1,650."
The context of this sentence indicates that what is meant is that the earned value (NOT the actual cost) is equal to $1,650.

Judi Doyle  Oct 18, 2014 
Printed Page 369
parenthetical instructions in item 1 of the "Sharpen your pencil" box at top of page

3rd edition, print

The text says "(Check your answer at the top of page 378 to make sure ..."

Page number should be 388.

Judi Doyle  Oct 18, 2014 
Printed Page 400
1. answer, explanatory text

The correct answer for this question is A ("Determine Budget") which is also listed as the correct answer.

However, in the text below the very same "Determine Budget" is discarded because "it uses the cost baseline and thus the cost baseline has to be created before". This is wrong! The cost baseline is actually the output of the "Determine Budget" process (see PMBOK guide) and not its input.
Instead the incorrect answer C ("Estimate Costs") is not mentioned at all - something got probably mixed up here…

Anonymous  Oct 27, 2015 
Printed Page 420
Remark on metric "Schedule variance"

"Schedule variance" is part of the "Cost Management" knowledge area, not "Time Management".

Robert Engelhardt  Oct 27, 2015 
Printed Page 420
Remark on metric "Schedule variance"

"Schedule variance" is part of the "Cost Management" knowledge area, not "Time Management".

Anonymous  Oct 27, 2015 
Printed Page 455
11. Answer: D explanation. Verify Scope happens in the Monitoring & Controlling Process

11. Answer: D explanation. Verify Scope happens in the Monitoring & Controlling Process.

Ruth Marzano  Oct 03, 2014 
Printed Page 464
1st paragraph

First paragraph on page 464 states: "Remember, in a matrix organization your team doesn't report directly to the project manager." However, the bottom right corner of page 42 states: "Folks who work in a balanced matrix organization report to a project manager AND a functional manager equally."

Mike Stewart  Mar 24, 2016 
Printed Page 519
Comment on output in the upper part of the page

The comment says (with an arrow to the Communcation Management Plan below): "This is the only output of the Plan Commucation Management process".
That is wrong. "Document Updates" is the second output (also listed in the PMBOK guide), the icon and text for exactly that second output are even on the same page! By the way, page 517 (talking of two outputs) has it correctly.

Anonymous  Oct 28, 2015 
Printed Page 527
2nd paragraph, 1st sentence

The text talks of "Direct and Manage Execution" - there is no such process! Either the "Direct and Manage Project Work" process is meant, or all processes in the overall "Executing Process Group".

Anonymous  Oct 29, 2015 
Printed Page 528
1st paragraph, 1st sentence

As this page is about the input of the process, the first sentence should probably read "Work performance data […]" (which is a valid input) instead of "Work performance information […]" (which is usually an output).

Anonymous  Oct 29, 2015 
Printed Page 532
clue for #7 down

Print
3rd edition

text has "communicaiton"; should be "communication"

Judi Doyle  Oct 25, 2014 
Printed Page 532
Clue for #10 across

"Pull" is not a "communication model" but rather a "communication method" (see also page 517).

Anonymous  Oct 29, 2015 
Printed Page 532
Clue for #11 down

"Push" is not a "communication model" but rather a "communication method" (see also page 517).

Anonymous  Oct 29, 2015 
Printed Page 554
Comment at the bottom on the input

The icon and text for one input denote the "Project Charter" (which is in accordance with the PMBOK guide), but the comment below speaks of the "(project) scope statement". That is different document and not the correct one to be mentioned here!

Anonymous  Oct 29, 2015 
Printed Page 566
"Brain Power" box at bottom of page

Printed
3rd edition

The "Brain Power" question asks, "Why do you think enterprise environmental factors are not an input to the Perform Qualitative Risk Analysis process?"

Enterprise environmental factors ARE an input to Qualitative Risk Analysis. They are illustrated as an input on that same page, and PMBOK 5, p. 312 confirms that.

Judi Doyle  Oct 25, 2014 
Printed Page 576
comment on formula in Step 3 at bottom of page

Print
3rd edition

Since the total EMV of the risks is positive ($30.70), you don't need to add contingency reserves to the budget to cover them, as the comment indicates. [Apparently, there was an arithmetic error here in the previous edition, and this number was shown as negative. The comment would make sense if this number were negative.]

Judi Doyle  Oct 25, 2014 
Printed Page 578
Bottom of page

Head First PMP, 3rd Edition, Updated for the 2016 PMP Exam
the book shows:
-$130 + -$333.55 + -$9.75 = $473.30
I think the EMV of the lighter tent should be negative:
-$130 + -$333.55 + -$9.75 = -$473.30

Steve Kato  Feb 15, 2017 
Printed Page 642
paragraphy under "Payment Systems" near top of page

Print
3rd edition

Text says "The payment system is how your company pays its sellers. It's usually established by an Accounting or Accounts Receivable department." Shouldn't that be an "Accounts Payable" department, if you are talking about paying your sellers?

Judi Doyle  Oct 27, 2014 
Printed Page 654
stem of question 8

Print
3rd edition

Text says "...and now you're working with the legal department at the buyer..."

The "at" should be "and"

Judi Doyle  Oct 27, 2014 
Printed Page 722
Question 27

The question asks, "Which best describes the COMMUNICATIONS process you are in" (emphasis added).

Answer B ("You did not identify a project stakeholder") is identified as the correct answer. But stakeholder identification is not one of the Communications Management processes, it is one of the Stakeholder Management processes.

Mike Stewart  Mar 30, 2016 
Printed Page 729
item 10 at bottom of page

Print
3d edition

"Lgitimate" should be "Legitimate"

Judi Doyle  Nov 01, 2014 
Printed, PDF Page 733
Answer for question 12.

Answer for question 12 should be B. 9 weeks as shown in explanation for question, instead of C. 12 weeks.

Sin Hua Wong  Mar 09, 2015 
Printed Page 733
Top of page

Both the answer and explanation for question 9 are incorrect. The correct answer should be "B. Lag", because two weeks are needed after finishing the equipment order, and starting the installation of the equipment. The PMBOK v. 5 defines lag as "the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.”

Mike Stewart  Mar 30, 2016 
Printed Page 734
Question 15 Explanation

The explanation for the CV states that "since the CV is negative, you're below your budget...".

However, a negative CV signals that you are over budget, not below it.

Mike Stewart  Mar 30, 2016 
Printed Page 823
comment at bottom of page

Print
3rd edition

"'Modified Agnoff Technique'" should be "'Modified Angoff Technique'". For the record, as of 11/01/2014, the PMP Handbook does not describe the standard setting technique used in establishing the pass score for the PMP exam.

Judi Doyle  Nov 01, 2014