Chapter 3Tools and Documentation (Domain 3.0)
- Which tool would you use to create a visual representation of timelines, start dates, durations, and activity sequence?
- Process diagram
- Pareto chart
- Gantt chart
- Histogram
- Which knowledge management tool would be used for a team to communicate instantly, share information on task ownership and status, and see events for an entire work group?
- Wiki pages
- Intranet sites
- Vendor knowledge bases
- Collaboration tools
- When dealing with a RACI chart, which of the following are true? (Choose three.)
- RACI is an acronym for responsible, accountable, consulted, and informed.
- RACI is a hierarchical and seniority-based matrix.
- RACI is an acronym for reasonable, accountable, conflicted, and informed.
Get CompTIA Project+ Practice Tests, 2nd Edition now with the O’Reilly learning platform.