- Just allowing the consequences of a negative risk to happen is which type of risk response strategy?
- Avoid
- Transfer
- Mitigate
- Accept
- What is the process of examining the risk and establishing the appropriate course of action should it occur called?
- Risk analysis
- Risk probability
- Risk response planning
- Risk trigger
- Kevin is working on a project and he wants to store information on a portable hard drive as a backup to his work computer. What two security considerations should he take into account while using removal media storage? (Choose two)
- Back up the data at a regular interval.
- Encrypt the removable hard drive to prevent unauthorized access.
- Lock the device in an out-of-view area ...