CHAPTER 5

Pre-installation Activities

In this chapter, you will learn about

• Conducting a site survey

• De-installing existing equipment

• Safety requirements

• Working with other trades

• Steps to escalate a problem

Conducting a site survey is one of the key activities in the pre-installation phases of an audiovisual (AV) systems integration project. Your objective during the site visit with the client is to discuss their general AV project expectations and review the characteristics of the various rooms and areas in which the AV components and systems will be installed. Make notes of all items that will help in the technical evaluation. The information you gather will also help in the evaluation of facility conditions and site preparation ...