Section 4Notification of delay

In this Section:

  • Giving notice of delay
  • Timing and contents of notice
  • Methods of notification
  • Supporting information
  • Timing of award

Giving notice of delay

The contractor must give notice to the architect that there is delay to the works. This notice must be given to the architect, except under DB2005, where it is to be given to the employer’s agent unless the employer has stated that it is to be given to the employer directly. Under MP2005 the notice must be given to the employer’s representative.

Contractor’s programme shows early completion

If the contractor’s programme shows that they are intending to finish the works before the date for completion and a delay occurs, the contractor should ...