SAP ASAP Methodology ◾ 395
3. Conduct Stress Tests.
4. Conduct Printing and Fax Tests.
5. Conduct Backup and Restore Procedure Tests.
6. Conduct Disaster Recovery Tests.
7. Conduct GoingLive Check.
13.2.4.5 Rene Cutover and Production Support Plan
e objective of this task is to rene the cutover and support plan devised during the Realization
Phase.
13.2.4.5.1 Prepare Detailed Cutover Plan
e purpose of this activity is to ascertain the readiness of the system and the company to go into
production. As pointed out earlier in this book, SAP implementation does not have any phase
analogous to the traditional phase of parallel runs. erefore, ...