Documentation of the Risk Data

Overrun likelihood (Y), worst case overrun duration (Δ), and the creep or step-overrun characteristic function cannot be casually approached! As with other information gathered throughout IPM project planning, task leaders again must: 1) review past projects, 2) talk to other experienced people, 3) review the baseline and actual Gantt charts from other similar projects, and 4) confer with all task team members in their quest for contribution data (this may take several days, given their other responsibilities). The project manager must be available during this time. A manager's advice and help, especially to people new to the procedure, is essential.

Each task leader will report this gathered information to the ...

Get Integrated Project Management now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.