SAMPLE QUESTIONS

Q: Question 29

The term PIR stands for:

(a) post implementation review;

(b) post initiation review;

(c) project initiation report;

(d) programme implementation report.

A: Discussion

This is a straightforward question if you are familiar with the PIR acronym. The correct answer is (a) as the aim is to identify lessons conducted from a post implementation review at the end of the IT-enabled change programme.

Q: Question 30

Which of the following is not a main source of documented information needed to do a formal review once implementation has taken place?

(a) The business case.

(b) Previous similar reviews.

(c) Stakeholder analysis.

(d) A summary of costs and benefits.

A: Discussion

A formal review after implementation will evaluate ...