Data load preparation

  • Purpose: The main motivation is to make plans and procedures to support the loading of data into the new system. During this period data cleansing is also performed.
  • Approach: SAP S/4HANA cloud.
  • Deliverable(s): Data migration scope and plan, specification for migration programs.
  • Tasks summary:
    • Based on scenario reviews, finalize the data requirement
    • Finalize the data sources and extraction and loading methods
    • Perform sata cleansing once the data to be loaded is analyzed
    • Develop the overall load plan, including sequence, expected data volumes, and expected load time
  • Accelerators: Data load planning template, data definition, data design, and data migration plan.