Timesheet Setup

Select the method of time reporting your organization wants to use and configure it for your organization's specific needs. Timesheet setup can be performed as follows:

1.
In PWA, select the Admin tab.
2.
Select Customize Project Web Access.
3.
Select Tracking Settings under Customization Options.

Specify the Default Method for Reporting Progress on Tasks

Three choices are available under the heading Specify the Default Method for Reporting Progress on Tasks: Percent Complete, Actual Work Done and Remaining Work, and Hours of Work Done Per Day or Per Week.

  • Percent Complete— Resources report the percent of work complete per task between 0% and 100%.

  • Actual Work Done and Remaining Work— Resources report the actual work done and ...