for developing pit limits. Within the pit are found materials of differing value. Economic
criteria are applied to assign destinations for these materials based on their value (i.e. mill,
waste dump, leach dump, stock pile, etc.). These criteria will be discussed. Once the pit
limits have been determined and rules established for classifying the in-pit materials, then
the ore reserves (tonnage and grade) can be calculated. In Chapter 6, the steps required to
go from the ore reserve to production rate, mine life, etc. will be presented.
5.2 HAND METHODS
5.2.1 The basic concept
Figure 5.2 showsan idealized cross-section through an orebody which outcrops at the surface
and dips to the left at 45
◦
. There are distinct physical boundaries separating the ore from
the over- and under-lying waste. The known ore extends to considerable depth down dip
and this will be recovered later by underground techniques. It is desired to know how large
the open-pit will be. The final pit in this greatly simplified case will appear as in Figure 5.3.
The slope angle of the left wall is 45
◦
. As can be seen a wedge of waste (area A) has been
removed to uncover the ore (area B). The location of the final pit wall is determined by
examining a series of slices such as shown in Figure 5.4.
For this example the width of the slice has been selected as 1.4 units (u) and the thickness
of the section (into the page) as 1 unit. Beginning with strip 1 the volumes of waste (V
w
)
and ore (V
o
) are calculated. The volumes are:
Strip 1:
V
w1
= 7.5u
3
V
o1
= 5.0u
3
The instantaneous stripping ratio (ISR) is defined as
ISR
1
(instantaneous) =
V
w1
V
o1
(5.1)
45°
Ore
Waste
5 Units
Figure 5.2. Cross-section through an idealized orebody.
Open pit mine planning and design: Fundamentals410