The map begins with G N K Enterprises placing a daily order and 180, 90, 60, and 30 day forecasts to the production control unit of Jensen Bearings Inc, which in turn sends a 4-week forecast and daily order for procurement of materials to Kline Steel Co.
A certain number of sheets are sent once a day to Jensen Bearings Inc. where the following process steps are carried out per Weekly Schedule charted by the production control unit.
The sheets are inventoried and pushed for pressing to generate W I P retainers 1050 L and 1200 S. These are inventoried for b days and pushed for piercing and forming to generate WIP retainers 250 L and 1500 S. These are inventoried for c days and pushed for finish grind to generate WIP retainers 500 ...