Each node is divided into four quadrants with each set of vertically placed quadrants separated by vertical strip representing the activity name and its estimated time. The four quadrants are as follows: Upper left: Earliest start time, E S
Lower left: Latest start time, L S
Upper right: Earliest finish time, E F
Lower right: Latest finish time, L F
There are 5 different paths from the start to finish. They are as follows:
From start to A, I, K, and to finish.
From start to A, F, K, and to finish
From start to A, C, G, J, K, and to finish.
From start to B, D, H, J, K, and to finish.
From start to B, E, J, K, and to finish.
The fourth path is a critical path.
The data are provided in the following table:
| Activity | Earliest start time ... |
|---|