Long description
The following are the approximate annual costs in dollars for the various plotted lot sizes:
Holding cost line is represented by Q divided by 2, times H. The coordinates are listed as follows:
Lot size | Annual cost |
---|---|
0 | 0 |
50 | 300 |
100 | 700 |
150 | 1,150 |
200 | 1,500 |
250 | 1,850 |
300 | 2,300 |
350 | 2,650 |
400 | 3,000 |
Ordering cost curve is represented by D divided by Q, times S. The coordinates are listed as follows:
Lot size | Annual cost |
---|---|
50 | 925 |
100 | 500 |
150 | 300 |
200 | 200 |
250 | 180 |
300 | 170 |
350 | 160 |
400 | 150 |
Total annual cost curve is represented by C = Q divided by 2, times H, plus, D divided by Q, times S. The coordinates are listed as follows:
Lot size | Annual cost |
---|---|
50 | 1,300 |
100 | 1,150 |
150 | 1,400 |
200 | 1,750 |
250 | 2,100 ... |