A flowchart depicts the component materials needed for the construction of product a. Component b, 3 units, and c, 1 unit, are needed in a lead time of 1. Component b is a product of components d, 1 unit and e, 2 units, and are needed in a lead time of 2. Component d has a lead time of 3, and e has a lead time of 6. Component c is a product of components f, 1 unit, and d, 1 unit, and are needed in a lead time of 3. Component f has a lead time of 1, and d has a lead time of 3. Component f is a product of component g, 1 unit. Component g has a lead time of 3.