Exam Prep Questions

Question 1 The ultimate responsibility for identifying and managing project risks rests with the ____________________.
  • A. Project sponsor

  • B. Project manager

  • C. Manager and sponsor

  • D. Project team

A1: Answer B is correct. Although the project manager shares this responsibility with all project stakeholders, the project manager has “ultimate” responsibility for this task. Therefore, answers A, C, and D are incorrect.
Question 2 A decision to augment the staff with independent consultants is an example of the interaction between which two project planning processes?
  • A. Resource planning and risk response planning

  • B. Organizational planning and procurement planning

  • C. Risk identification and procurement planning

  • D. Staff acquisition ...