Chapter 10. Answers to Practice Exam 1
Answer D is the best response. You have a responsibility to refrain from accepting inappropriate forms of compensation for personal gain. Answers A and C are incorrect for this reason. Answer B is a poor choice because the appearance of impropriety is present. | |
Answer D is the correct response. A work breakdown structure (WBS) is not a component of the project charter. Answers A, B, and C are all components of the project charter. | |
Answer A is the best response. A project manager should be assigned prior to the start of project planning. Answer B is incorrect because the project manager should be assigned prior to the creation of a project charter. Answer C is incorrect because a project manager should ... |