Assessment Test

  1. The project sponsor has approached you with a dilemma. At the annual stockholders meeting, the CEO announced that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and now stockholders expect implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. Choose the best action from the options listed to speed up the project.
    1. Hire more resources to get the work completed faster.
    2. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources.