Answers to Assessment Test

  1. D. Fast-tracking is the best answer in this scenario. Budget was the original constraint on this project, so it's unlikely the project manager would get more resources to assist with the project. The next best thing is to compress phases to shorten the project duration. For more information, please see Chapter 1.
  2. A. Discretionary dependencies can create arbitrary total float values, and they can also limit scheduling options. For more information, please see Chapter 4.
  3. A. Project managers spend about 90 percent of their time communicating through status meetings, team meetings, email, verbal communications, and so on. For more information, please see Chapter 9.
  4. B. Inspections are also called reviews, peer reviews, ...