TIME MANAGEMENT

The following information and questions 1 through 10 refer to figure 1.

Figure 1. Scheduling Practice Exercise.

A schedule was developed for a project to install windows in an apartment building. The project is a rush job, and the contractor has agreed to schedule the work on a single shift basis but will work seven days per week until the job is done. The project is to begin on May 1.

1:What day in May will activity D have for its early finish date?
  1. May 13

  2. May 6

  3. May 7

  4. May 5

2:What is the free float for activity F?
  1. 6

  2. 7

  3. 0

  4. 8

3:What is the free float for activity D?
  1. 6

  2. 7

  3. 8

  4. 0

4:What is the critical path of the project?
  1. A B E G H

  2. A B D F H

  3. A C G H ...