Risk Identification

The identification of the risk is very important. Each must be described in detail so that it will not be confused with any other risk or project task that must be done. Each risk should be given an identification number. During the course of the project, as more information is gathered about the risk, all of this information can be consolidated about the particular risk.

The first component we need to discuss is the identification of the risk event. In the course of identifying risk events we will call upon the project team, subject matter experts, the stakeholders, and other project managers. Much of the work already done in the project will be utilized in the risk management process. Among these items that will be used ...