255 System Cost Uncertainty Analysis
6.8 Review Case Discussion 6.2 and verify the computations that led to the
correlation between Cost
Sys
and PrgmSched.
6.9 The coordinates listed below are the 20 points shown in Figure 6.7. They
are values for (x, F
Cost
Sys
(x)) determined by the Monte Carlo simulation.
The simulation was run with a sample size of n = 5000.
(27.88, 0.05), (28.72, 0.10), (29.44, 0.15), (29.97, 0.20), (30.45, 0.25),
(30.9, 0.30), (31.3, 0.35), (31.74, 0.40), (32.2, 0.45), (32.64, 0.50),
(33.07, 0.55), (33.43, 0.60), (33.87, 0.65), (34.41, 0.70), (34.99, 0.75),
(35.6, 0.80), (36.29, 0.85), (37.39, 0.90), (38.72, 0.95), (45.71, ...