All of the inputs and outputs in this section appear in alphabetical order; therefore, no sections numbers are assigned.

Accepted deliverables. Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.

The authorized stakeholder who signs off and approves the deliverables should get involved early on in the process and provide feedback regarding the quality of the deliverables so that the team can assess quality, performance, and recommend necessary changes.

Activity attributes. Activity attributes are multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes ...