144 use bY ProsPeCtive Program managers
© 2011 by Taylor & Francis Group, LLC
ELEMENT 3.10 A PROGRAM MANAGEMENT OFFICE (PMO) IS APPROVED AND IMPLEMENTED
A B C D
10. Program management
elements and artifacts to
use should be included in
the:
PWBS Scope
statement
Program
charter
Requirements
document
ELEMENT 3.11 TOOLS, PROCESSES, AND TECHNIQUES REQUIRED FOR PROGRAM MANAGEMENT
ARE OBTAINED
A B C D
11. One approach to manage
program data and
information is to:
Prepare a
program
reporting
plan
Use the same
status reports
for all
stakeholders
Use the
EPMO
Establish a
PMIS
ELEMENT 3.12 THE PROGRAM MANAGEMENT PLAN IS APPROVED
A B C D
12. The program management ...