Appendix

Glossary

activity
Also known as task, an individual step performed to reach a project’s goal.
actual
Final reporting data for a task, such as the date when the task really started versus its planned start date or the amount of work completed versus the planned amount of work.
ACWP (actual cost of work performed)
Cost of the actual, real work done on a task, work package, or project to date.
ALAP (as late as possible)
A constraint put on a task’s timing to make the task occur as late as possible in the project schedule, taking into account any dependency relationships.
analogous estimate
An estimating method that takes information from past similar projects into consideration when developing estimates for the current project.
ASAP (as soon as possible)
A constraint put on a task’s timing to make the task occur as early as possible in the project schedule, taking into account any dependency relationships. This is the default constraint type.
automatically scheduled (auto-scheduled)
A task mode where Project calculates the schedule as needed based on task dependencies, constraints, and resource availability.
BAC (budget at completion)
The sum total of all costs involved in completing a task, work package, or project. See also baseline cost.
Backstage view
The area that presents files and options when you click the File tab.
baseline
The formally agreed-upon dates for starting, finishing, duration, work, and cost data in the project. Later, actual schedule and duration, work, ...

Get Project 2016 For Dummies now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.