29.  The five Project Management Process Groups are:

A. Planning, checking, directing, monitoring, and recording.

B. Initiating, planning, executing, monitoring and controlling, and closing.

C. Planning, executing, directing, closing, and commissioning.

D. Initiating, executing, monitoring, evaluating, and closing.

30.  Project Management Process Groups are:

A. Overlapping activities that occur throughout the project.

B. Overlapping activities that generally occur at the same level of intensity within each phase of the project.

C. Generally discrete, one-time events.