Project Time Management

(Chapter 6 of the PMBOK® Guide)

66. Answer: B.

PMBOK® Guide, page 141, Introduction; and page 143, Figure 6-1

Project Time Management

Project Time Management includes the processes required to manage the timely completion of the project.

Figure 6-1 provides an overview of the Project Time Management processes, which are as follows:

6.1 Plan Schedule Management—The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

6.2 Define Activities—The process of identifying and documenting the specific actions to be performed to produce the project deliverables.

6.3 Sequence Activities—The process of identifying and documenting ...