Project Time Management

(Chapter 6 of the PMBOK® Guide)

66.  The Project Time Management processes include:

A.  Activity Definition, Activity Sequencing, Activity Execution, Activity Duration Estimation, and Activity Control.

B.  Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, and Control Schedule.

C.  Identify Activities, Develop Schedule, Execute Activities, Control Activities, and Monitor Schedule Results.

D.  Determine Activities, Estimate Activity Durations, Develop Schedule, Implement Activities, and Report Activity Results.

67.  In rolling wave planning:

A.  Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.

B.  The ...