Project Procurement Management

(Chapter 12 of the PMBOK® Guide)

199. Answer: C.

PMBOK® Guide, pages 360–364, Section 12.1.1; and page 358, Figure 12-2

Plan Procurement Management: Inputs

.1 Project Management Plan

.2 Requirements Documentation

.3 Risk Register

.4 Activity Resource Requirements

.5 Project Schedule

.6 Activity Cost Estimates

.7 Stakeholder Register

.8 Enterprise Environmental Factors

.9 Organizational Process Assets

200. Answer: A.

PMBOK® Guide, page 368, Section 12.1.3.3

Procurement Documents

Procurement documents are used to solicit proposals from prospective sellers. Terms such as bid, tender, or quotation are generally used when the seller selection decision will be based on price (as when buying commercial or standard items), ...