61.All of the following are true about the project scope management plan EXCEPT:

A.It enables the creation of the WBS from the detailed project scope statement.

B.It describes how the scope will be defined, developed, monitored, controlled, and validated.

C.It can be formal or informal, broadly framed or highly detailed, based on the needs of the project.

D.It is not related to the project management plan.

62.Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. All of the following are true about this process EXCEPT:

A.The project's success is directly influenced by active stakeholder involvement ...