Long description
Each item has the following components listed:
Gross
On hand
Net
Order receipt
Order release
Numbers for each component are listed in the week column, and a lead time is identified based on those numbers. The chart reads, row by row descending, as follows:
Item AA
-
Gross, a 10 in week 6
On hand zero, a zero in week 6
Net, a 10 in week 6
Order receipt, a 10 in week 6 with an arrow pointing to
Order release, a 10 in week 5
Lead time is 1 week
-
Item A
-
Gross, a 50 in week 6
On hand 10, a 10 in week 6
Net, a 40 in week 6
Order receipt, a 40 in week 6 with an arrow pointing to
Order release, a 40 in week 5
Lead time is 1 week
-
Item B
-
Gross, an 80 superscript A in week 5
On hand 15, a 15 in week 5
Net, a 65 in week 5
Order receipt, ...
-