Long description

In the network diagram:

  • A start node is present on the extreme left.

  • Boxes A, C, and F with the descriptions Build internal components, construct collection stack, and Install Pollution Control System are seen at the top, adjacent to each other.

  • Boxes B, D, and G with the descriptions Modify Roof and Floor, Pour Concrete and Install Frame, and Install Air Pollution Device are seen at the bottom, adjacent to each other.

  • Boxes E and H with the descriptions Build High-Temperature Burner and Inspect and Test Pollution Control System are seen underneath the boxes C and F.

  • Two arrows from the start node lead to the boxes A and B.

  • An arrow from box A leads to box C.

  • An arrow from box B leads to box D.

  • Two arrows from box C lead to boxes ...