Cost Performance Reports Analysis
Cost performance reports (CPRs) have become useful in uncovering areas in which technical problems are causing variances. In these reports, team members explain cost and schedule variances using narrative to indicate the specific problem causing the variance. Many of the variances reported can signal risk situations as they are developing, such as late vendor or subcontractor deliveries. Continuing these types of schedule slips can put an entire project schedule at risk. Normally, project managers are limited in what they can do to alleviate these situations except when the sponsoring organization is causing the delays. In such cases, high-level coordination with the sponsoring organization ...