“Do I Know This Already?” Quiz

1. B. Risks will not yet have been identified, but the documentation structures that will house them should already be in place. It’s one of the first actions of the risk manager.

2. C. Although the information the project manager generates will become crucial to building the risk register, if the project manager has taken on the role of risk librarian, they must share that information openly and freely with all the relevant stakeholders.

3. B. Organizational mission and vision statements are normally not project-specific and thus don’t play into the document base for project risk identification. The other data cited here ...