APPENDIX

The Detailed Planning Model

In Chapters 6 to 8 we explored a six-step model for developing a detailed project plan. The example for this model, the home landscape project, was spread over these three chapters. To make it easier to see the steps of planning, the home landscape project example is repeated here, beginning with the detailed planning model in Figure A.1 and following the stages through to completion (Figures A.2 through A.6).

FIGURE A.1 Detailed planning model.

image

FIGURE A.2 Develop a work breakdown structure, sequence the tasks, and estimate the work packages.

image

FIGURE A.3 Step Four: Calculate an initial schedule.

image

FIGURE A.4A Gantt chart with resource spreadsheet for home landscape project.

image
image

FIGURE A.5A Step Five: Assign and level resources.

image
image