146
The PMP® Certification Exam Study Guide - Rosaldo de Jesus Nocêra
INTEGRATION
The process of reviewing all change requests, approving changes and managing changes to the deliverables,
organizational process assets, project documents, and the project management plan.
Monitoring and controlling
4.5 - Perform Integrated Change Control
Tools and
techniques
OutputsInputs
Changerequestlog
Changeprocessdocuments
Changerequests
4.2 - Develop Project
Management Plan
4.3 - Direct And Manage
Project Execution
4.4 - Monitor And Control
Project Work
5.4 - Verify Scope
5.5 - Control Scope
6.6 - Control Schedule
7.3 - Control Costs
8.2 - Perform Quality
Assurance
8.3 - Perform Quality
Control
9.4 - Manage Project
Team
10.4 - Manage
Stakeholder Expectations
10.5 - Report
Performance
11.6 - Monitor And
Control Risks
12.1 - Plan
Procurements
12.2 - Conduct
Procurements
12.3 - Administer
Procurements
Projectmanagementplan
•Workperformanceinformation
•Changerequests
Change control
meetings
Project
management plan
updates
4.2 -Develop Project
Management Plan
4.3 - Direct and
Manage Project
Execution
8.3 - Perform Quality
Control
12.3 - Administer
Procurements
Change requests
status updates
Project document
updates
Project
documents
Expert
judgment
Enterprise/Organization
•Enterpriseenvironmental
factors
•Organizationalprocessassets
Process group
INITIATING PLANNING EXECUTING
MONITORING AND
CONTROLLING
CLOSING
Chapter 4 - Project Integration Management
147
The PMP® Certification Exam Study Guide - Rosaldo de Jesus Nocêra
4.7 INTEGRATION MANAGEMENT IN PROJECT CLOSING


Close Project or Phase
4.7.1 CLOSE PROJECT OR PHASE PMBOK® GUIDE, PROCESS 4.6
e Close Project or Phase process involves all the activities of project completion or a given
phase of the project. is process establishes procedures for coordinating activities necessary to
verify and document project deliverables, verifying and documenting the reasons for the project
cancellation before completion (aborted), if any.
e projects are closed for a range of reasons, including
ose successfully concluded,
ose canceled before completion (aborted), and
ose transformed in continuous operation.


by the operation.


             
extinction. Examples of Closing by exhaustion may be the order cancellation by the
customer and the appearance of higher priority projects.


4.7.1.1 CLOSE PROJECT OR PHASE: INPUTS, TOOLS AND TECHNIQUES, AND OUTPUTS
INPUTS
 
e project management plan and its auxiliary plans depict the main input for this
process.
 
            
process.
 
          

148
The PMP® Certification Exam Study Guide - Rosaldo de Jesus Nocêra
TOOLS AND TECHNIQUES
 
Expert opinion may be used as an aid in the process execution to close the contract, by

OUTPUTS
 
Contract closure must only occur upon formal acceptance and delivery of the product,
service, or result in the contract.
 
           
          

lessons learned from the project.
Chapter 4 - Project Integration Management
149
The PMP® Certification Exam Study Guide - Rosaldo de Jesus Nocêra
INTEGRATION
The process of nalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.
Closing
4.6 - Close Project or Phase
Tools and
techniques
OutputsInputs
4.2 - Develop Project
Management Plan
Projectmanagementplan
Organizational
process assets
updates
Final product,
service or
result transition
Expert
judgment
5.4 - Verify Scope
Accepteddeliverables
Enterprise/Organization
•Organizationalprocessassets
Customer
•Projectles
•Projectorphaseclosure
documents
•Historicalinformation
Process group
INITIATING PLANNING EXECUTING
MONITORING AND
CONTROLLING
CLOSING
Enterprise/Organization
This page intentionally left blankThis page intentionally left blank