76 Section 4
4.4.1.2 SCHEDULE VARIANCE
Schedule variance (SV) is a measure that reflects the difference between the amount of work planned to be
accomplished and the amount of work actually accomplished at the present time. It answers the following management
questions related to time performance:
 Is the amount of work performed more or less than planned to date?
 Was more or less time spent than planned based on the amount of work accomplished?
 How much more or less time was spent than planned?
The amount of work is measured in budget value using the unit of measure selected (see Section 4.3). SV can be
expressed in both volume of work (SV ...
Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Project Stakeholder Management

Project Stakeholder Management

Pernille Eskerod, Anna Lund Jepsen
Rethink! Project Stakeholder Management

Rethink! Project Stakeholder Management

Martina Huemann, Pernille Eskerod, Claudia Ringhofer

Publisher Resources

ISBN: 9781628256390