Enterprises are becoming aware that they do not need to adhere to a single methodology (e.g., predictive or
adaptive approaches), which has led to the creation of hybrid concepts (see also Section 3.5). However, the project
manager may be responsible for managing several concurrent, high-visibility projects or CAs using a mixture of
plan-driven (i.e., predictive) and agile (i.e., adaptive) methods in a fast-paced environment that may cross multiple
business divisions.
4.4.3.1 SUPPLEMENTING AGILE REPORTING WITH EVM
Traditional agile metrics (see Section 5.4 of the Agile Practice Guide) do not provide ...