138 APPENDIX X4
X4.4 EXECUTING AND MONITORING AND CONTROLLING A PROJECT USING EVM
As noted in Section 3, the example project starts off within the first CA (CA-001) in the first WP, Project Management
(WP-01). All other resources are in planning packages in CA-001 and the other CAs. The example uses rolling wave
planning and then details are planned for the rest of CA-001 and CA-002, followed by detail planning for CA-003 to
CA-005 during the project planning phase that occurs within CA-002.
Although no detailed planning has been accomplished beyond CA-001 and WP-01, project work starts with CA-001/
WP-01 and the project moves into the use of executing ...
Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Project Stakeholder Management

Project Stakeholder Management

Pernille Eskerod, Anna Lund Jepsen
Rethink! Project Stakeholder Management

Rethink! Project Stakeholder Management

Martina Huemann, Pernille Eskerod, Claudia Ringhofer

Publisher Resources

ISBN: 9781628256390