143
X4.4.3 WEEK 44 (YEAR 1)
At this point, all the CAs in the PMB (CA-001, CA-002, CA-003, and CA-004) are open with numerous work packages
(see Table X4-4 and Figure X4-3).
CA-003, especially WP-08 (Civil Works), has completed 3 weeks early, which the team was able to predict because
they were tracking EV using the construction contractor’s table of values as a physical measure of completed work.
The work completed early from the start of the WP. This allowed the team to plan to start several other WPs early per
the schedule network.
The Scrum team started CA-004 3 weeks early (week 40), which was possible because the team was able to
predict early ...
Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Project Stakeholder Management

Project Stakeholder Management

Pernille Eskerod, Anna Lund Jepsen
Rethink! Project Stakeholder Management

Rethink! Project Stakeholder Management

Martina Huemann, Pernille Eskerod, Claudia Ringhofer

Publisher Resources

ISBN: 9781628256390