Book description
This user friendly guide introduces, explains, and demystifies the NEC4 contract on a practical, work-based level. Made for architects by an architect, it explores the best approach to collaborative and contractual partnering work practices.
Table of contents
- Cover
- Title
- Copyright
- Contents
- About the author
- Introduction
- 1 Background to the NEC
-
2 Structure and content of NEC4
- ‘Pick-and-mix’ assembly of the contract
-
Core clauses
- Core Clause Section 1: General
- Core Clause Section 2: The Contractor’s main responsibilities
- Core Clause Section 3: Time
- Core Clause Section 4: Quality management
- Core Clause Section 5: Payment
- Core Clause Section 6: Compensation events
- Core Clause Section 7: Title
- Core Clause Section 8: Liabilities and insurance
- Core Clause Section 9: Termination
- Main option clauses
-
Secondary option clauses
- Secondary Option X1: Price adjustment for inflation
- Secondary Option X2: Changes in the law
- Secondary Option X3: Multiple currencies
- Secondary Option X4: Ultimate holding company guarantee
- Secondary Option X5: Sectional Completion
- Secondary Option X6: Bonus for early Completion
- Secondary Option X7: Delay damages
- Secondary Option X8: Undertakings to the Client or Others
- Secondary Option X9: Transfer of rights
- Secondary Option X10: Information modelling
- Secondary Option X11: Termination by the Client
- Secondary Option X12: Multiparty collaboration
- Secondary Option X13: Performance bond
- Secondary Option X14: Advanced payment to the Contractor
- Secondary Option X15: The Contractor’s design
- Secondary Option X16: Retention
- Secondary Option X17: Low performance damages
- Secondary Option X18: Limitation of liability
- Secondary Option X20: Key Performance Indicators
- Secondary Option X21: Whole life cost
- Secondary Option X22: Early Contractor involvement
- Secondary Option Y(UK)1: Project Bank Account
- Secondary Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
- Secondary Option Y(UK)3: The Contracts (Rights of Third Parties) Act 1999
- Secondary Option Z: Additional conditions of contract
- Options W1, W2 and W3: Dispute resolution options
- Contract Data
- Schedule of Cost Components
- Scope
- Site Information
- The Agreement
- 3 Contract machinery
-
4 Collaborative working with NEC4
-
Professional services
- Relationship to the building contract
- Application of the PSC for any discipline of Consultant
- Cultural and procedural change
- Responsibility, authority and people organisation
- Multidisciplinary and project-specific nature of the Scope
- No conventional percentage fee basis
- Fine-tuning a PSC Consultant’s role
- Subcontracting
- Project profiles
- Partnering
- Framework agreements
- Management systems
-
Professional services
- 5 International use
- 6 In conclusion: decisive features of NEC4
- Appendix: NEC4 ‘Toolkit’
- Index
Product information
- Title: Architect's Guide to NEC4
- Author(s):
- Release date: June 2019
- Publisher(s): RIBA Publishing
- ISBN: 9781000701319
You might also like
book
Sustainability, Energy and Architecture
This unique volume offers insights from renowned experts in energy efficient building from the world over, …
book
Design
It will be invaluable for architectural students at Part 3 who are getting to grips with …
book
Fundamentals of Building Construction: Materials and Methods, 5th Edition
Now in its Fifth Edition, this essential textbook has been used by thousands of students annually …
book
Graphic Design Process
The process of creating graphic design cannot be easily defined: each designer has their own way …