38 Best Practices & Methodology for Electronic Software Distribution & Operating System Provisioning
come to light during the detailed study and planning tasks. The scope of the
Estimated Preliminary Costs addresses:
The estimated software costs to the client
The estimated hardware costs to the client
The estimated implementation and integration costs to the client
The timing and order of installation based on a high-level implementation plan
The estimated total costs of the system for software, hardware, and services
All assumptions used in calculating the costs and schedule
The preliminary costing process is iterative throughout the selection phase and
will be finalized prior to the integration phase of the project.
The development of the Estimated Preliminary Costs can vary widely depending
on the scope and size of the project. The Estimated Preliminary Costs is usually
the initial cost document for the discussion, planning, and acquisition of the new
system. The original numbers will be approximates that are refined as the actual
requirements become known. Early in the Estimated Preliminary Costs task, the
Project Manager should meet with the Client Team Manager and appropriate
client financial personnel to identify and address the basis and purpose of the
numbers. Typically, these numbers are “list” prices from the vendors and illustrate
typical hardware, implementation and support costs. During the final definition
phase and negotiations, these numbers may change significantly.
Agreement
An agreement is the formal definition of the mutual commitments of the delivery
organization performing the service, and the sponsor or requestor of service, and
of a subcontractor and the delivery organization or of other parties, such as
co-contractors. There can be more than two parties to an agreement.
The structure and content of the agreement can vary markedly from project to
project. In particular, agreements with external sponsors and subcontractors are
usually very different from those with internal organizations.
Resources Assigned to Plan
Resources Assigned to Plan
is not a work product but a task to ensure that the
required resources are assigned to the project plan for executing a specified
Change Request.
2.4.6 Develop ESD preliminary deployment plan
The purpose of the Develop ESD preliminary deployment plan activity of the
ESD Change Request process is to review resources and change requirements
for the purpose of developing an initial plan, to develop building blocks of the