4.2. Programmatic Recovery Checklist
Table 4-1 is the Programmatic Recovery Checklist. Use this table to find and isolate a problem in the programmatic part of your project. The Programmatic Performance Checklist is presented in Chapter 2 of this book.
1 | STATEMENT OF WORK (SOW) | Recovery | Yes |
---|---|---|---|
1a (NO) | The SOW was not properly defined | 59 | |
1b (NO) | The SOW is not within our capabilities | 60 | |
1c (NO) | The SOW was not properly interpreted | 62 | |
1d (NO) | The SOW was not properly negotiated | 64 | |
1e (NO) | The SOW is not being properly monitored | 65 | |
1f (NO) | The SOW is not being performed properly | 66 |
2 | SPECIFICATION | Recovery | Yes |
---|---|---|---|
2a (NO) | The Specification was not properly defined | 67 | |
2b (NO) | The Specification is not within our capabilities | 69 | |
2c (NO) ... |