RECOVERY

Because line design, processes, and materials are interrelated, they must each be shown to be proper or improper to isolate the problem and fix it. This involves five steps:

First:Isolate line design by eliminating processes and materials.
Second:Isolate the part of the line that is contributing to the problem.
Third:Fix the problem.
Fourth:Research the processes and materials and ensure that they are still compatible.
Fifth:Make a trial run to ensure that all are compatible.

If necessary, iterate the process. When you are satisfied that the process is correct, return to full production

58c (NO) Shop Orders were not correct or thorough

Shop Orders were not correct or thorough when the end product produced is not the product that was specified ...