RECOVERY

Each testable unit should have its own requirement (Specification). This is true whether the unit will be built internally or by subcontract. The subcontract will contain procurement data in excess of the requirement (Specification) but will otherwise be the same.

The requirement (Specification) should be the basis of a Test Plan for the unit. The Unit Test Plan must define the:

  • Test performance figures, standards, etc., that the unit must meet

  • Conditions under which the test will be run

  • Support equipment

  • Test equipment

  • Conditions for acceptance of the test

  • Process for documenting and resolving test discrepancies

  • The details and step-by-step process of the test itself

Test Plans vary widely in their composition and content, but the definitions ...

Get Blueprint for Project Recovery: A Project Management Guide The Complete Process for Getting Derailed Projects Back on Track now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.