RECOVERY
The first step in this process is to create a CSF Checklist. Begin by creating a matrix as shown in Table 5-2. Notice that the requirement is in the far left column and the final proof is in the far right column. Scour the requirements document (contract) for requirement inputs and complete that column first.
CSF | Unit A | Unit B | Unit C | Unit D | Final Proof |
---|---|---|---|---|---|
MTTR 0.5 hrs | 0.5 hrs | 0.5 hrs | 0.5 hrs | 0.5 hrs | RMA Analysis Para 3.2.1 |
MTBF 30,000 hrs | 30,000 hrs | 30,000 hrs | 30,000 hrs | 30,000 hrs | RMA Analysis Para 3.2.2 |
Consider using the "shalls" list created in Attachment 7 to assist in your requirement inputs.
The second step is to follow the requirement through the WBS and make a columnar entry in the matrix to reflect ...