Appendix D
Memory Tables Answers
Chapter 2
Table 2-3 Business Risk vs. Reward vs. Cost Analysis
Design Decision |
Associated Cost |
Design Complexity |
Business Risk |
Business Reward |
Single points of failure |
Low; no additional cost for redundancy. |
Low |
Very high; outages are more likely to occur that would directly bring the business offline, which would make the business lose revenue and market reputation. |
Low; initial cost savings. |
No single points of failure |
Medium; the solution cost increases to allow for redundant components to mitigate any single points of failure. |
High |
Low; the solution has been designed to allow for single failures to occur that would still allow the business to function and make money. |
High; the initial cost is ... |