Chapter 6Practice Test 2
- Which project management role is responsible for product integrity and ensures conformance to standards and specifications?
- Developer/engineers
- Business analyst
- Testers/quality assurance specialists
- Architect
- Which of the following is not a communication trigger?
- Project planning
- Kickoff meeting
- Milestones
- Schedule changes
- A potential future event that can have either a negative or positive impact on a project is known as which one of the following?
- A risk
- A deliverable
- A requirement
- An issue
- What risk tolerance would a start-up in the technology industry likely have?
- Risk taker
- Risk avoider
- Gambler
- Moderate risk tolerance
- As part of the preparation to begin work on a project, the project manager makes ...
Get CompTIA Project+ Practice Tests, 2nd Edition now with the O’Reilly learning platform.